Hall County has spent much of what it has currently pledged for the Gateway Industrial Centre, according to a presentation at the board of commissioners’ Monday work session.
The county has about $6.6 million in funds it has awarded to contractors for roads, water lines, storm water lines and construction. It has spent about $3 million so far for Phase I and Phase II work installing infrastructure inside the 518-acre park. The county committed to $10 million in improvements to the industrial park, including water, sewer, storm systems and roadways.
With more than $6 million already committed, the county has slightly less than $4 million to establish sewer service for the park in North Hall.
via Gateway Industrial Centre making costly progress.