Citing shoddy work that may take months and more taxpayer dollars to fix, DeKalb County shut down work Friday on the first major project of its $1.35 billion water/sewer overhaul.
The Atlanta Journal-Constitution began asking questions about the $7.7 million excavating contract with Desmear Systems earlier this week, after learning the Tucker company had first struggled to secure a performance bond, then later provided a bond that turned out to be fraudulent. Lack of a bond would mean the county could have difficulty recovering any money it lost on the project.
Despite those problems, DeKalb gave Desmear the go-ahead in July 2012 to blast away granite and prepare land next to the Snapfinger wastewater treatment plant in south DeKalb for a $250 million expansion. The work is designed to help DeKalb plan for future growth and serve any home or business south of Decatur that flushes a toilet.
But problems ran far deeper than how the contract was awarded, according to county inspection records and meeting notes obtained exclusively by the AJC.
via DeKalb pulls plug on major sewer project amid quality concerns | www.myajc.com.